Hello,
It varies depending on the jurisdiction. If no zoning process is required (building permit only), the process to NTP can take as little as a few months. But with zoning, it can take 6 months to 24 months, although most are less than 12 months.
As an FYI, other steps must be done besides zoning/permitting before an NTP can be issued. (procurement of power, telco, materials)
It varies depending on the jurisdiction. If no zoning process is required (building permit only), the process to NTP can take as little as a few months. But with zoning, it can take 6 months to 24 months, although most are less than 12 months.
As an FYI, other steps must be done besides zoning/permitting before an NTP can be issued. (procurement of power, telco, materials)