Answer
![Ken Schmidt](https://data3.answerbase.com/answerbase/6488/UserFiles/User1580446/profileImage1580446.jpg?635701525440000000)
Sep 27, 2017 - 04:19 AM
Hi,
Depends upon the location and whether there are local zoning codes or not. With zoning- figure 9-12 months on average. Without zoning, 6 months.
Thanks
Ken